WORKS:
Substation lifter 115/13.8 kV.
24-32 MVA autotransformer.
115 kV feeder for the transmission line that links this installation with the Camargo II substation.
Evacuation line 115 kV 0.65 km-line.
Installation of a circuit in self-supporting towers with VOLTAE-design under Mexican and international regulations.
DETAIL OF SERVICES:
Detailed engineering: civil and electromechanical of the line and substation.
Technical office.
EPCM of the interconnection: Management and supervision of the work, control and programming. Purchase Management
Start-up assistance.
Energía
Ingeniería
__
Interconnection engineering of 30 MW photovoltaic plant.
Client_ Gran Solar