WORKS:
Substation lifter PER I-IV. 400 / 34.5 kV
Substation lifter PER I-IV. 400 / 34.5 kV
Evacuation line of the Reynosa I-IV – substation Airport wind farm. 400 kV. 29.6 km-line. Installation of two circuits in towers and self-supporting posts.
Deviation LT Airport – Cumbres Frontera-Ventika-Ternium. 400 kV and 230 kV. 1.04 km-line.
Substation Manoeuvres Airport. 400 kV.
Four feeders in 400 kV for transmission lines.

DETAIL OF SERVICES:
Property Engineering.
Review of civil and electromechanical detailed engineering of lines and substations. Review of medium voltage of wind farms.